Brentex has completed so far, over 80% of actual pipeline construction works, including crossings, and that it is working with NNPCL (Owner), barring any challenge, to deliver all the stations, by the first quarter of 2025, except 2 Terminal Gas Stations (TGS), which are under descope conversation between Owner and BCL.